Status Report — N 296th repair and infrastructure improvement project

12 Sunday Sep 2021

Posted by RVH Board in Improvements, Roads

≈ Comments Off on Status Report — N 296th repair and infrastructure improvement project

Dear RVH Residents and Neighbors,


Cactus Asphalt has finally been able to schedule our repair and infrastructure improvement project relating to the storm damage that occurred along N 296th Ave.

 
The work is scheduled for Oct 11 – 15.  The work is expected to take the entire week. A single lane will remain open to traffic throughout except for momentary closures due to equipment movement.


A notice will be sent to all residents and neighbors again just prior to the start of work as a reminder to please drive slowly and use care when passing through the work zone.


The attached aerial view is an artist’s conception of the scope of the project as it will appear when completed.
Thanks for your patience.  All contractors are swamped with work right now for a variety of reasons.  And it has taken much longer than expected to develop and review the design and to complete the bidding, RVH Board review and approval process and then scheduling.  That is all now complete. We are in the queue to have our work done as soon as possible.

Regards,
Bill Owens

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Traffic Alert – Road Clean-up on Tuesday, August 3

31 Saturday Jul 2021

Posted by RVH Board in Roads

≈ Leave a comment

Update:  Cactus Asphalt will be cleaning mud and debris from our entire roadway system on Tuesday, August 3.  The work crew is expected to be present for the entire day starting at 7:30 AM and continuing until around 5 PM.

Residents are requested to please reduce travel speeds and use caution when approaching the workers and equipment.  The work crew will involve two tractors, two mechanized brooms and a water truck to facilitate removal of heavy mud.  So please use caution when passing the work crews.

Road closures are not expected; although, there may be brief interruptions to travel due to movement of equipment.

Please be patient and show extra courtesy and care to the work crews.

Thank you,

Brett Gerasim

RVH HOA President

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Traffic Alert Update – RVH Road Clean-up Delayed

27 Tuesday Jul 2021

Posted by RVH Board in Roads

≈ Leave a comment

Due to the severe storms in the valley over the weekend, Cactus Asphalt will be delayed in cleaning our roads.  It will not happen on July 28 as originally planned. 

We will let you know as soon as we have a new date and expect it will be within a few days.

Thank you,

Brett Gerasim

RVH HOA President

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Traffic Alert – RVH Road Clean-up 7/28

26 Monday Jul 2021

Posted by RVH Board in Roads

≈ Leave a comment

Cactus Asphalt will be cleaning mud and debris from our entire roadway system on Wednesday, July 28.  The work crew is expected to be present for the entire day starting at 7:30 AM and continuing until around 5 PM.

Residents are requested to please reduce travel speeds and use caution when approaching the workers and equipment.

Road closures are not expected; although, there may be brief interruptions to travel due to movement of equipment.

Please be patient and show extra courtesy and care to the work crews.

Thank you,

Brett Gerasim

RVH HOA President

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

RVH Road Clean-up and Repairs – Status Report

26 Monday Jul 2021

Posted by RVH Board in Around the Neighborhood, Roads

≈ Leave a comment

As you all are aware, Rio Vista Hills was hit on July 21st with a major thunderstorm that has left our roadways covered with mud and debris with severe edge-of-road damage in many areas.  3 inches of rain fell in a span of 2 hours.  People in the neighborhood say they have never in 20 years experienced such a storm.  Since then, there have been additional downpours adding to the problems. 

Following is our status report regarding clean-up and repair actions.  Residents wishing to volunteer their assistance with these activities are urged to contact Brett Gerasim.  There is much to do.

Road Clean-up

Clean-up activities will begin later this week with most areas expected to be cleaned of mud and debris no later than Friday, July 30, 2021.  As more rain is expected in coming weeks, we anticipate additional clean-up work to be performed as needed later-on.

Cactus Asphalt will perform the clean-up activity this week and will utilize a crew with two kick brooms and two smaller tractors each equipped with a front loader bucket and a Gannon.  The tractor operators will set the Gannon to about ½ to 1 inch above the road.  The tractors will move mud, larger gravel and rock off the road.  The kick brooms will follow and will clean the remainder of the mud and gravel.  It has been emphasized that the tractor operators be very careful with the grading equipment to not damage our asphalt road surfaces.  With this crew, it is believed the bulk of the RVH roads can be cleaned in one day.  The highest travel areas of the road system will be top priority.  Second priority will be lesser traveled areas that have the most problematic debris.  There may be some roads with minimal debris that will not get serviced in this first phase of work.

Please drive with extra caution while the road debris is present and be especially careful and alert when the work crews are on-site later this week.  Thank you in advance for your cooperation and care.

Erosion Damage on N 296th

This serious erosion site is located along N 296th Avenue just up the road North of Stevens’ driveway entrance.  Sandbags have been placed around the damaged area to slow further erosion while we await a permanent solution.  Warning signs are also in place.  Traffic reduces to one lane nearest the hillside when passing this area.  Unless we have another unusually heavy rainstorm, we believe significant further erosion is unlikely at this site and we believe the lane nearest the hillside is safe for use.  Please drive with care and be respectful of oncoming traffic in this zone.

Design concepts for a permanent solution are in work and are expected to be completed by July 30.  We expect a formal bid from Cactus Asphalt no later than August 6.  Our goal is to start the permanent repair work as soon as we are satisfied with the design and related costs.  Our goal is to have all the work at this repair site completed within the month of August.

Other Road Damage and Edge Erosion

Our priority has been to have clean-up activities in place and to have design concepts in work for fixing the N 296th erosion site.  There are a vast number of additional areas along our roads where edge erosion is serious and must be dealt with.  In coming weeks we expect to have a list of these additional areas needing work and will start to prioritize and plan for those repairs. 

We will keep you updated regarding our additional repair plans and activities. 

At this time, while the costs of all the clean-up and repairs are expected to be considerable, we believe the HOA will have sufficient funds to stay on schedule with the major road resurfacing project planned for April/May 2022. The damage caused by this storm has made it even more important to keep the resurfacing project on track for 2022.

Regards and please drive with care,

Brett Gerasim

RVH HOA President

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Traffic Alert for N. 293rd and N. 295th Ave

29 Tuesday Jun 2021

Posted by RVH Board in Improvements, Roads

≈ Leave a comment

The APS contractor began excavation work for repairs to the underground cable on N 293rd avenue today, Tuesday June 29th. This will be followed by excavation on N 295th between Nicoulin’s residence and the first intersection.


Residents should please reduce travel speeds and use caution in construction zones.


Residents should expect brief power outages over the next few weeks as lines are tested and restored to use. 


Please be patient and show extra courtesy and care to the work crews. The duration of this work is not known at this time but could stretch to a few weeks.


Thank you,
Brett Gerasim
RVH HOA President

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Announcement Regarding Recent Power Failures

20 Sunday Jun 2021

Posted by RVH Board in Around the Neighborhood, Roads

≈ Comments Off on Announcement Regarding Recent Power Failures

In the last 72 hours RVH residents and neighbors have experienced 2 extended power failures. In both cases an underground cable suffered a failure. The first failure occurred between the first intersection and the transformer at Miller’s driveway along 294th Avenue. The second failure took place between the transformer across from Nicoulin’s residence and the transformer at the first intersection along 295th Avenue.

Nearly 1/2 mile of temporary power cable has been laid above ground at these failure locations. There is one cable crossing 295th Avenue near the intersection.

Residents are asked to reduce speed and use caution when driving in these locations.

Please be watchful for APS work crews at either location. The power cables that serve our community are now 50 years old. When we receive information regarding line replacement action and planned interruption of service you will be informed.

Thank you,

Brett Gerasim

RVH HOA President

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Street Sweeping Alert for Tuesday, 12/22

21 Monday Dec 2020

Posted by RVH Board in Roads

≈ Leave a comment

Dear Rio Vista Hills HOA Members and Neighbors,
On Tuesday December 22 Cactus Asphalt will be performing the annual sweeping all of our roads in Rio Vista Hills. They will start work around 7 AM and will continue all day. Please drive very carefully and be observant of equipment and personnel in the roadway.

For more information, please contact Robert Stringfellow at 714-292-9550.
Thank you in advance for your cooperation.
Best Regards,
The RVH HOA Board
December 21, 2020

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Traffic Alert

20 Sunday Dec 2020

Posted by RVH Board in Improvements, Roads

≈ Leave a comment

Starting the week of December 21, APS will be trenching and installing
new cable along the branch of N295th that runs from the Southwest
corner of Stringfellow’s lot all the way up the branch to Glinski’s
property. This work is expected to continue for several weeks.
Please drive slowly and carefully in the construction area and be alert
to equipment and personnel that may be in the roadway.
For more information please contact Robert Stringfellow 714-292-9550
The RVH HOA Board

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Traffic Alert for 7/3 – 7/4/20

30 Tuesday Jun 2020

Posted by RVH Board in Roads

≈ Comments Off on Traffic Alert for 7/3 – 7/4/20

TRAFFIC ALERT — Friday, July 3rd and 4th

On Friday, July 3rd and Saturday, July 4th there will be a crew of workers at our entrance to repair the stucco on the entry arch columns and retaining walls. The initial phase of the work is expected to be completed on those two days.

Please drive slowly and be especially careful when driving through the area when workers are present.

Thank you in advance for your care and cooperation.

Regards,

Bill Owens
RVH Board Secretary

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...
← Older posts
Newer posts →

Subscribe

  • Entries (RSS)
  • Comments (RSS)

Archives

  • December 2022
  • October 2022
  • September 2022
  • June 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • July 2021
  • June 2021
  • February 2021
  • December 2020
  • June 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • August 2019
  • March 2019
  • February 2019
  • May 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • October 2017
  • September 2017
  • August 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • November 2016
  • March 2016
  • February 2016
  • January 2016
  • November 2015
  • May 2015
  • February 2015
  • January 2015
  • November 2014
  • January 2014
  • December 2013
  • September 2013
  • January 2013
  • December 2012
  • July 2012

Categories

  • Annual Meeting
  • Around the Neighborhood
  • Improvements
  • Introduction
  • Meetings
  • Resources
  • Roads
  • Uncategorized

Meta

  • Register
  • Log in

Blog at WordPress.com.

  • Follow Following
    • Rio Vista Hills HOA
    • Already have a WordPress.com account? Log in now.
    • Rio Vista Hills HOA
    • Customize
    • Follow Following
    • Sign up
    • Log in
    • Report this content
    • View site in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...
 

    %d bloggers like this: